Khyndai Lad junction: from concept to ribbon-cutting in 14 months
How one of the city's worst T-junctions was redesigned — and what we'd do differently next time.

Khyndai Lad — the junction outside the IGP's office — used to be where Police Bazaar's morning rush went to die. Three uncoordinated signal phases, no pedestrian refuges, and a drainage gully running diagonally across the southbound approach. Average wait time at 09:15 in 2024: 142 seconds. Average wait time today: 58 seconds.
What we changed
Four arms, all rebuilt. Pedestrian refuges on every arm, raised at footpath level. Signal control replaced with an adaptive controller that talks to the engine and pulls priority for buses tagged on Route 1 and Route 5. A real-time information display added on the southbound side because, frankly, the queue was going to be there sometimes and people deserve to know how long it'll be.
What worked
What we'd do differently
The numbers
| Metric | Before | After |
|---|---|---|
| AM peak avg wait (s) | 142 | 58 |
| PM peak avg wait (s) | 168 | 71 |
| Pedestrian crossing time (s) | 22 | 14 |
| Bus on-time % | 64% | 78% |
The work cost ₹18.4 crore and took 14 months. It will pay back, in time saved alone, in roughly 22 months. Nobody designs a junction for the payback period — but it doesn't hurt that it pays back.
— PMU, Engineering Wing